Vulnerability Analysis of Activities and a Two-Stage Approach for Stochastic Multi-Mode Resource-Constrained Project Scheduling

Document Type : Research Paper

Authors
1 Department of Industrial Engineering, Faculty of Industrial and Systems Engineering, Tarbiat Modares University, Tehran, Iran
2 Department of Industrial Engineering, Faculty of Engineering, Bu-Ali Sina University, Hamedan, Iran
Abstract
Projects are inherently subject to various uncertainties and disruptions, which are among the main causes of project completion delays and reduced reliability of the initial schedule. However, in real-world project environments, activities are not equally affected by disruptions, and ignoring these differences can lead to inefficient resource allocation and unnecessary cost overruns. This study proposes a novel approach to assessing activity vulnerability and vulnerability-based resource acquisition in the multi-mode resource-constrained project scheduling problem with stochastic activity durations. In the first stage, 11 network-based, temporal, and resource-based indicators are extracted and weighted using the Shannon entropy method. The vulnerability level of each activity is then calculated as a weighted combination of these indicators. Based on this, a heuristic algorithm is developed to acquire renewable resources, prioritizing activities with higher vulnerability and determining the purchase quantity as a function of the vulnerability index, resource tightness, and maximum resource requirement. Once the purchase quantities are determined, the proposed mixed-integer linear programming (MILP) model is solved to make scheduling and resource allocation decisions under uncertainty. Computational results show that the vulnerability-based resource acquisition strategy reduces makespan compared to no acquisition, while the two-stage heuristic-exact approach significantly reduces computational time compared to solving the MILP model directly. These findings highlight that identifying vulnerable activities plays a key role in enhancing the robustness of project scheduling.
Keywords

[1]    کاتبی، علی؛ الماسیان، فریبرز؛ همامی، پیمان، (1398). زمان‌بندی پروژه‌های ساخت با منابع محدود (MRCPSP) با درنظر گرفتن عدم قطعیت در مدت زمان فعالیت‌ها و تأخیرات، مهندسی سازه و ساخت، 6، 17698.
[2]    Cao, F., Servranckx, T., He, Z., Vanhoucke. M. (2025). A buffer allocation evolutionary algorithm for resource-constrained projects with activity clusters, Journal of Scheduling, 28: 483–511
[3]    Wang A. (2019). A framework for assessing project vulnerability to crises, International Journal of Managing Projects in Business, 12: 1079 – 1096.
[4]    Guo, N., Guo, P., Shang, J., Zhao, J. (2020). Project vulnerability analysis: A topological approach. Journal of the Operational Research Society, 71:1233–42.
[5]    Aleksic, A., Puskaric, H., Tadic, D., Stefanovic, M. (2017). Project management issues: vulnerability management assessment. Kybernetes, 46: 1171-1188.
[6]    Zarghami, SA., Gunawan, I., Corral de Zubielqui, G., Baroudi, B. (2020). Incorporation of resource reliability into critical chain project management buffer sizing. Int J Prod Res, 58: 6130-6144
[7]    Goldratt EM. (1997). Critical Chain, The North River Press.
[8]    Milat, M., Knezic, S., Sedlar, J. (2021). A new surrogate measure for resilient approach to construction scheduling. Procedia Comput. Science.,181:468-476.
[9]    Chaari, T., Chaabane, S., Aissani, N., Trentesaux, D. (2014). Scheduling under uncertainty: Survey and research directions. International Conference on Advanced Logistics and Transport (ICALT), 229-234.
[10] Liu, H., Qu, S., Li, R., Razaa, H. (2021). Bi-objective robust project scheduling with resource constraints and flexible activity execution lists, Computers & Industrial Engineering, 156: 107288.
[11] پرچمی افرا، خیرخواه امیرسامان. (1402). ارائه الگوریتم آزادسازی لاگرانژ برای مسأله زمان‌بندی چندپروژه‌ای با محدودیت منابع، برنامه‌ریزی سفارش‌دهی و برنامه‌ریزی تولید منابع مصرفی در زنجیره تامین پروژه محور. مجله تحقیق در عملیات در کاربردهای آن (ریاضی کاربردی)، 20:33-60.
[12] Talbot, F.B. (1982).  resource-constrained project scheduling with time-resource tradeoffs: the nonpreemptive case, Management Science, 28: 1197 – 1210.
[13] Artigues, C., Hartmann, S., Vanhoucke, M. (2026). Fifty years of research on resource-constrained project scheduling explored from different perspectives, European Journal of Operational Research, 328.
[14] Rodríguez-Ballesteros, S., Alcaraz, J., Anton-Sanchez, L. (2026). Multi-mode resource-constrained project scheduling problem with time-dependent resource costs and capacities: A bi-objective approach, Expert Systems with Applications, 306:130955.
[15] باقرزاده رحمانی، سارا، رضائیان، جواد، ابراهیمی، احمد. (1404). زمان‌بندی دوهدفه پروژه‌ها با گروه‌های کاری چندمهارته، اثر یادگیری و زمان‌های راه‌اندازی و پردازش وابسته به گروه کاری. نشـریه پـژوهـش‌های مهنـدسـی صنــایع در سیستـم‌هـای تولیــد، 26:1935.
[16] Khoshsirat, M., Mousavi, S.M. (2024). A new proactive and reactive approach for resource-constrained project scheduling problem under activity and resource disruption: a scenario-based robust optimization approach, Annals of Operations Research, 338:597–643
[17] Kobylański, P., Kuchta, D. (2007). A note on the paper by MA Al-Fawzan and M. Haouari about a bi-objective problem for robust resource-constrained project scheduling, International Journal of Production Economics, 107: 496 – 501.
[18] Chtourou, H., Haouari, M. (2008). A two-stage-priority-rule-based algorithm for robust resource-constrained project scheduling, Computers & Industrial Engineering, 55: 183-194
[19] Hao, X., Lin, L., Gen, M. (2014). An effective multi-objective EDA for robust resource constrained project scheduling wih uncertain durations, Procedia Computer Science, 36: 571 – 578.
[20] Russell, M.M., Hsiang, S.M., Liu, M., Wambeke, B. (2014). Causes of time buffer and duration variation in construction project tasks: comparison of perception to reality, Journal of Construction Engineering and Management, 140: 04014016
[21] Bahnas, N., Adel, K., Khallaf, R., Elhakeem, A. (2024). Monitoring and controlling engineering projects with blockchain-based critical chain project management, Automation in Construction, 165: 105484
[22] She, B., Chen, B., Hall, N.G. (2021). Buffer sizing in critical chain project management by network decomposition, Omega, 102: 102382.
[23] Lotfi, R., Vaseei, M., Ali, S.S., Davoodi, S.M.R., Bazregar, M., Sadeghi, S. (2024). Budget allocation problem for projects with considering risks, robustness, resiliency, and sustainability requirements, Results in Engineering, 24:102828.
[24] Artigues, C., Michelon, P., Reusser, S. (2003). Insertion techniques for static and dynamic resource-constrained project scheduling, European Journal of Operational Research, 149: 249 – 267.
[25] Policella, N. (2005). Scheduling with uncertainty: A proactive approach using partial order schedules, AI Communications, 18: 165 – 167.
[26] Liang, Y., Cui, N., Hu, X., Demeulemeester, E. (2020). The integration of resource allocation and time buffering for bi-objective robust project scheduling, International Journal of Production Research, 58: 3839 – 3854.
[27] Rohaninejad, M., Tavakkoli-Moghaddam, R., Vahedi-Nouri, B. (2015). Redundancy resource allocation for reliable project scheduling: A game-theoretical approach, Procedia Computer Science, 64: 265-273.
[28] Shariatmadari, M., Nahavandi, N. (2020). A new resource buffer insertion approach for proactive resource investment problem, Computers & Industrial Engineering, 146: 106582.
[29] Hu, X., Cui, N., Demeulemeester, E., Bie, L. (2016). Incorporation of activity sensitivity measures into buffer management to manage project schedule risk, European Journal of Operational Research, 249: 717 – 727.
[30] Li, H., & Demeulemeester, E. (2016). A genetic algorithm for the robust resource leveling problem. Journal of Scheduling, 19(1), 43-60
[31] Gwak, H. S., Bea, S. H., & Lee, D. E. (2018). Resource Leveling using Genetic Algorithm. Korean Journal of Construction Engineering and Management, 19(1), 3-13
[32] Liu, W., Zhang, J., Qu, C., & Zhang, H. (2024). Performance of Priority Rules for Finance-Based and Resource-Constrained Project Scheduling Heuristics. Journal of Construction Engineering and Management, 150(6), 04024047
[33] Li, C., Wang, F., & Chung, T. (2024). Multi-mode multi-skill resource-constrained project scheduling problem with differentiated professional capabilities. Journal of Project Management, 9(1), 27–44
[34] Kolisch, R., Sprecher, A. (1997). PSPLIB – A project scheduling problem library: OR software – ORSEP operations research software exchange program, European Journal of Operational Research, 96: 205 – 216.
[35] Jarboui, B., Damak, N., Siarry, P., Rebai, A. (2008). A combinatorial particle swarm optimization for solving multi-mode resource-constrained project scheduling problems, Applied Mathematics and Computation, 195: 299 – 308.
[36] Shen, H., Li, X. (2013). Cooperative discrete particle swarms for multi-mode resource-constrained projects, 2013 IEEE 17th International Conference on Computer Supported Cooperative Work in Design (CSCWD), Whistler, BC, Canada: 31 – 36.
[37] Li, H., Zhang, H. (2013). Ant colony optimization-based multi-mode scheduling under renewable and nonrenewable resource constraints, Automation in Construction, 35: 431 – 438.
[38] de la Pisa, M.P., Molina, J.C., Eguía, I. (2024). Ant colony algorithms for minimizing costs in multi-mode resource constrained project scheduling problems with spatial constraints, International Journal of Industrial Engineering Computations, 15: 667 – 684.
[39] Geiger, M.J. (2017). A multi-threaded local search algorithm and computer implementation for the multi-mode, resource-constrained multi-project scheduling problem, European Journal of Operational Research, 256: 729 – 741.
[40] Damak, N., Jarboui, B., Siarry, P., Loukil, T. (2009). Differential evolution for solving multi-mode resource-constrained project scheduling problems, Computers & Operations Research, 36: 2653 – 2659.
[41] Song, Y., Vanhoucke, M. (2025). Schedule risk analysis for project control with risk interactions, Annals of Operations Research,1-56
[42] Kahraman, C., Onar, S.C. (2015). Intelligent techniques in engineering management, Springer.
[43] Zhu, J., Mostafavi, A. (2014). A system-of-systems framework for performance assessment in complex construction projects, Organization, Technology & Management in Construction: An International Journal, 6: 0.
[44] Shannon, C. E. (1948). A mathematical theory of communication. Bell System Technical Journal, 27(3), 379–423.
[45] Tavares, L.V., Antunes Ferreira, J.A., Silva Coelho, J. (1998). On the optimal management of project risk, European Journal of Operational Research, 107: 451 – 469.
[46] Trietsch, D., Mazmanyan, L., Gevorgyan, L., Baker, K.R. (2012). Modeling activity times by the Parkinson distribution with a lognormal core: Theory and validation, European Journal of Operational Research, 216: 386 – 396.
[47] Artigues, C., Roubellat, F. (2000). A polynomial activity insertion algorithm in a multi-resource schedule with cumulative constraints and multiple modes, European Journal of Operational Research, 127: 297 – 316.
[48] Bartusch, M., Möhring, R.H., Radermacher, F.J. (1988). Scheduling project networks with resource constraints and time windows, Annals of Operations Research, 16: 199 – 240.